Roads17GG0027

REHAB/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4, CONCRETE RECONSTRUCTION OF POTOTAN-TINA-LAMBUNAO ROAD, K0032+060 - K0032+237 ; K0032+381-K0032+426 ; K0

REHAB/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4, CONCRETE RECONSTRUCTION OF POTOTAN-TINA-LAMBUNAO ROAD, K0032+060 - K0032+237 ; K0032+381-K0032+426 ; K0 is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱34,480,681.84. Status: Reported complete (DPWH). Contractor on record: ROPRIM CONST CORP FORMERLY ROPRIM CONST. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱39,030,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
(Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers), along Jalaur River, Brgy. Imbang Pequeño, Sta. 0+000 - Sta. 0+359, San Enrique, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-17-0025289

₱1,049,184.00 · FY2017

Released to Marinduque Distr Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱34,480,681.84

Progress

Reported complete (DPWH)

Start Date

March 31, 2017

Target End

August 8, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.