Buildings and Facilities20AI0129

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, ASINGAN, PANGASINAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, ASINGAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱3,839,953.45. Status: Reported complete (DPWH). Contractor on record: A P TAGARINO ENGINEERING AND CONST SERVICES. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱27,427,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Facility for Brgy. Poblacion, Bani, Pangasinan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Pangasinan 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,839,953.45

Progress

Reported complete (DPWH)

Start Date

October 5, 2020

Target End

January 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.