Flood Control and Drainage24J00284

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (TUGBUNGAN SECTION), ZAM-BOANGA CITY, PACKAGE 4 is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱96,200,102.35. Status: Past target date (DPWH On-Going). Contractor on record: PYRAMID CONSOLIDATED BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

131 projects · ₱5.8B total · 0 flags

4. Implementation

Contract Amount

₱96,200,102.35

Progress

Past target date (DPWH On-Going)

Start Date

January 13, 2025

Target End

December 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.