Roads22PG0020

CONSTRUCTION/IMPROVEMENT OF CUDOG-MUNGAYANG-KIANGAN ROAD LEADING TO AMBUAYA LAKE, YAMASHITA SHRINE AND KIYANGAN SETTLEMENT, KIANGAN AND LAGAWE, IFUGAO

CONSTRUCTION/IMPROVEMENT OF CUDOG-MUNGAYANG-KIANGAN ROAD LEADING TO AMBUAYA LAKE, YAMASHITA SHRINE AND KIYANGAN SETTLEMENT, KIANGAN AND LAGAWE, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱12,740,000.00. Status: Reported complete (DPWH). Contractor on record: LN BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,660,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Boliwong Flood Control Structure, Sta. 3+750-Sta. 3+900 and Sta. 4+782-Sta. 5+182, Lagawe, Ifugao
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Ifugao 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

7 projects · ₱97.9M total · 0 flags

4. Implementation

Contract Amount

₱12,740,000.00

Progress

Reported complete (DPWH)

Start Date

February 11, 2022

Target End

October 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.