Construction of Flood Mitigation Structure24IB0018

Construction of Llorente Flood Control Structure, K0977+400 - K0978+000, Llorente, Eastern Samar

Construction of Llorente Flood Control Structure, K0977+400 - K0978+000, Llorente, Eastern Samar is a DPWH-tracked public work in CITY OF BORONGAN (CAPITAL) (EASTERN SAMAR), EASTERN SAMAR, Region VIII. Reported contract value: ₱77,199,970.50. Status: Reported complete (DPWH). Contractor on record: JAMA88 BUILDERS INC / P B OBIAL CONST. Figures trace to sumbong.

CITY OF BORONGAN (CAPITAL) (EASTERN SAMAR), EASTERN SAMAR, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Taft, Eastern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008716

₱1,842,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0001636

₱180,616.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008715

₱170,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱77.2M total · 0 flags

4. Implementation

Contract Amount

₱77,199,970.50

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

September 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.