BIP: CONSTRUCTION OF WATER SYSTEM (LEVEL II) AT BARANGAY 66 - BANQUEROHAN, LEGAZPI CITY, ALBAY

BIP: CONSTRUCTION OF WATER SYSTEM (LEVEL II) AT BARANGAY 66 - BANQUEROHAN, LEGAZPI CITY, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱4,793,925.69. Status: Past target date (DPWH On-Going). Contractor on record: MACROPRIME BUILDERS CORP FORMERLY: MORANTE BUILDERS. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Suha Flood Control Dike, Camalig, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Water System (Level II) at Barangay 66 - Banqueroh

₱4,793,925.69 · MACROPRIME BUILDERS

Contractor

D

33 projects · ₱658.0M total · 0 flags

4. Implementation

Contract Amount

₱4,793,925.69

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2022

Target End

May 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.