Roads19KB0025

WIDENING ALONG SAYRE HIGHWAY, K1540+(-294)-K1540+(-194), K1562+208-K1562+294, 1) MUSUAN, DOLOGON, MARAMAG, BUKIDNON AND 2) CAMP I, MARAMAG, BUKIDNON

WIDENING ALONG SAYRE HIGHWAY, K1540+(-294)-K1540+(-194), K1562+208-K1562+294, 1) MUSUAN, DOLOGON, MARAMAG, BUKIDNON AND 2) CAMP I, MARAMAG, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱10,149,860.00. Status: Reported complete (DPWH). Contractor on record: RRN CONSTRUCTION. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-19-0004088

₱270,000.00 · FY2019

Released to Burak National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Probable match · 86%

14K00284

₱9,650,938.32 · RRN CONSTRUCTION

4. Implementation

Contract Amount

₱10,149,860.00

Progress

Reported complete (DPWH)

Start Date

June 28, 2019

Target End

October 5, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.