Roads24IA0014

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1050+375 TO K1050+854

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1050+375 TO K1050+854 is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱33,650,070.15. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Amambahag Flood Control along Biliran Circumferential Road, Phase VII, Culaba, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Biliran DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱33,650,070.15

Progress

Reported complete (DPWH)

Start Date

February 11, 2024

Target End

September 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.