Construction of Flood Mitigation Structure24CF0012

Construction of Flood Mitigation Structure along Pampanga River, Barangay Sapang Buho, Palayan City, Nueva Ecija

Construction of Flood Mitigation Structure along Pampanga River, Barangay Sapang Buho, Palayan City, Nueva Ecija is a DPWH-tracked public work in PALAYAN CITY (CAPITAL) (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱85,114,741.23. Status: Reported complete (DPWH). Contractor on record: JERRY R SANTIAGO CONST CORP FORMERLY: JERRY SANTIAGO CONST. Figures trace to sumbong.

PALAYAN CITY (CAPITAL) (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱25,354,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Casongsong River, Barangay Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0002880

₱6,100,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007112

₱1,895,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017683

₱578,300.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007113

₱175,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

58 projects · ₱1.6B total · 1 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT/REHABILITATION/COMPLETION OF VARIOUS MULTI-PURPOSE BUILDINGS (COVERED COURT, BRGY. HALL, EVACUATION CENTER), CALAPAN CITY, ORIENTAL MINDORO

Mindoro Oriental DEO, Region IV-B

2022₱131.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - STA. ROSA - TARLAC RD - K0108 + (-881) - K0108 + (-803), K0111 + 100 - K0111 + 832, K0112 + 576.50 - K0113 + 082, K0116 + 000 - K0117 + 724

Nueva Ecija 2nd DEO, Region III

2024₱89.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS NUEVA ECIJA - AURORA RD. - K0131+007-K0131+843, K0132+066-K0133+000, K0133+233-K0134+500, K0135+835-K0136+461, K0137+900-K0138+144, K0139+2

Nueva Ecija 2nd DEO, Region III

2023₱86.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - NUEVA ECIJA - AURORA RD - K0129+543-K0129+743, K0129+743-K0129+995, K0130+000-K0131+000, K0131+700-K0131+997.50, K0132+000-K0132+11

Nueva Ecija 2nd DEO, Region III

2024₱86.6M
Reported complete (100% progress, DPWH status On-Going)

Rehabilitation of Digmala River Control, Brgy. Tugatog, Bongabon, Nueva Ecija

BONGABON (NUEVA ECIJA), NUEVA ECIJA, Region III

2022₱82.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD NET ALONG LRR/SF TO MOLAVE, PHILIPPINE ARMY, FORT MAGSAYSAY, PALAYAN CITY, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2020₱81.2M
Reported complete (DPWH)
View all 58 projects →

4. Implementation

Contract Amount

₱85,114,741.23

Progress

Reported complete (DPWH)

Start Date

February 13, 2024

Target End

November 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.