Flood Control and Drainage18CJ0065

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/DESILTING OF UNGOT CREEK, TARLAC CITY (PHASE VI)

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/DESILTING OF UNGOT CREEK, TARLAC CITY (PHASE VI) is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱46,549,712.79. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Desilting of Ungot Creek, Tarlac City (Phase VI)
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-18-0013294

₱468,675,741.00 · FY2018

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

328 projects · ₱20.7B total · 0 flags

4. Implementation

Contract Amount

₱46,549,712.79

Progress

Reported complete (DPWH)

Start Date

February 5, 2018

Target End

August 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.