Buildings and Facilities23IA0042

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, KAWAYAN, BILIRAN (11.678875, 124.357023; 11.678854, 124.35673

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, KAWAYAN, BILIRAN (11.678875, 124.357023; 11.678854, 124.35673 is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱4,838,754.25. Status: Past target date (DPWH On-Going). Contractor on record: 4K VERMARK CIVIL ENGINEERING CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay San Lorenzo, Kawayan, Biliran
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Biliran DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,838,754.25

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2023

Target End

June 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.