Buildings and Facilities19JF0051

CONSTRUCTION OF MPB (BRGY. HALL), BRGY. SAN JOSE, MUNICIPALITY OF R.T. LIM ZAMBOANGA SIBUGAY

CONSTRUCTION OF MPB (BRGY. HALL), BRGY. SAN JOSE, MUNICIPALITY OF R.T. LIM ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱1,481,394.98. Status: Reported complete (DPWH). Contractor on record: GJD CONST. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0025380

₱476,000.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱1,481,394.98

Progress

Reported complete (DPWH)

Start Date

July 25, 2019

Target End

October 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.