Roads23BH0253

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. GUD TO BRGY. RIZAL EAST, SAN ISIDRO, ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. GUD TO BRGY. RIZAL EAST, SAN ISIDRO, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱14,475,000.00. Status: Reported complete (DPWH). Contractor on record: PILASTRO BUILDERS. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gumbaun-San Isidro Flood Control Project, Echague - San Isidro, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,475,000.00

Progress

Reported complete (DPWH)

Start Date

December 11, 2023

Target End

May 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.