Bridges19DD0026

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE-WIDENING OF PERMANENT BRIDGES, ICARBANG BR. (B03114LZ) ALONG SN JUAN- LAIYA RD.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE-WIDENING OF PERMANENT BRIDGES, ICARBANG BR. (B03114LZ) ALONG SN JUAN- LAIYA RD. is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱14,259,268.65. Status: Reported complete (DPWH). Contractor on record: REVERE CONST. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Released to Bata National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

118 projects · ₱5.2B total · 0 flags

4. Implementation

Contract Amount

₱14,259,268.65

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

October 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.