Roads16FF0010

REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PILI-TIGAON-ALBAY BOUNDARY ROAD (CONSTRUCTION OF SLOPE PROTECTION) K0500+300-K0500+400; K0504+500-K0504+673; K0504+800-K0504+900 PATITINAN, SAGÑAY, CAMARINES SUR

REHABILITATION/RECONSTRUCTION OF NATIONAL ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PILI-TIGAON-ALBAY BOUNDARY ROAD (CONSTRUCTION OF SLOPE PROTECTION) K0500+300-K0500+400; K0504+500-K0504+673; K0504+800-K0504+900 PATITINAN, SAGÑAY, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱28,310,385.32. Status: Reported complete (DPWH). Contractor on record: ALRO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation and Improvement of Camaligan Flood Control (Bicol River), Brgy. Mangayawan, Canaman, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027986

₱243,341.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

91 projects · ₱5.7B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, BRGY. BUDIAO, DARAGA, ,ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱184.5M
Past target date (DPWH On-Going)

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, UPSTREAM OF CAMALIG BRIDGE, BRGY. 4 (POB)-QUIRANGAY, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱159.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY BATANG, IROSIN, SORSOGON

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GABAO RIVER, BARANGAY GABAO

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱154.3M
Past target date (DPWH On-Going)
View all 91 projects →

4. Implementation

Contract Amount

₱28,310,385.32

Progress

Reported complete (DPWH)

Start Date

March 13, 2016

Target End

October 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.