Buildings and Facilities22CJ0119

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SINILIAN 2ND, CAMILING, TARLAC

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SINILIAN 2ND, CAMILING, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱4,802,621.01. Status: Reported complete (DPWH). Contractor on record: ENYE CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Camiling River Left Bank Phase II-2, Poblacion D to G Section, Poblacion D to G, Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Tarlac DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,802,621.01

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

June 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.