Flood Control and Drainage19BD0091

PROTECTIVE LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER, TUGUEGARAO SECTION, NAMABBALAN, CAGAYAN, DOWNSTREAM

PROTECTIVE LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER, TUGUEGARAO SECTION, NAMABBALAN, CAGAYAN, DOWNSTREAM is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱62,989,494.72. Status: Reported complete (DPWH). Contractor on record: EGB CONST CORP FORMERLY: EGB CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-19-0018277

₱250,056.00 · FY2019

Released to School (Davao del Sur National High School) 0911230 - Digos City National High (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

646 projects · ₱29.0B total · 49 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY

Region II, Region II

2025₱241.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0399 + 008 - K0400 + 009, K0405 + 885 - K0406 + 340, K0439 + 000 - K0439 + 557, K0444 + 230 - K0447+ 200, K0447 + 7

Region II, Region II

2024₱213.3M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MANSALAY COASTAL ROAD, DEL MUNDO SECTION, MANSALAY, ORIENTAL MINDORO

Region IV-B, Region IV-B

2023₱212.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- MINDORO WEST COASTAL ROAD, K0417+000 - K0445+498 (INTERMITTENT SECTIONS), ABRA DE ILOG, OCC. MINDORO

Region IV-B, Region IV-B

2025₱202.1M
Past target date (DPWH On-Going)
No sat.

CSSP-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF TUROD-BANQUERO BRIDGE, REINA MERCEDES, ISABELA

Isabela 3rd DEO, Region II

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF DIVERSION/BY-PASS ROAD OF CORY AQUINO BOUL

Region V, Region V

2025₱192.0M
Past target date (DPWH On-Going)
View all 646 projects →

4. Implementation

Contract Amount

₱62,989,494.72

Progress

Reported complete (DPWH)

Start Date

July 29, 2019

Target End

July 2, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.