Buildings and Facilities19AG0227

CONSTRUCTION OF MODIFIED STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING AT DON MATIAS ES, BURGOS, PANGASINAN

CONSTRUCTION OF MODIFIED STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING AT DON MATIAS ES, BURGOS, PANGASINAN is a DPWH-tracked public work in Pangasinan 1st DEO, Region I. Reported contract value: ₱9,870,007.80. Status: Reported complete (DPWH). Contractor on record: JONIK TRADING. Figures trace to dpwh.

Pangasinan 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0020532

₱0.00 · FY2019

Released to Zamboanga Sibugay National High School (Pangi NHS) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

415 projects · ₱3.3B total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION/CONSTRUCTION OF ROADS, CITY OF ALAMINOS, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱98.0M
Past target date (DPWH On-Going)

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURES IN BALINGCAGUING RIVER (POBLACION EAST SECTION), BRGY. POBLACION EAST, AGNO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE, PANGASINAN-ZAMBALES RD - K0284+000 - K0285+000, K0299+000 - K0300+000, K0321+000 - K0323+000, K0325+088 - K0325+300, K0326+400 - K0327+034, K0327+228 - K0328+000, K0329+000 - K0329+240.9

Region I, Region I

2019₱61.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - RECONSTRUCTION OF MULTI-PURPOSE BUILDING, DON RAYMUNDO CELESTE SPORTS COMPLEX, BARANGAY GERMINAL, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2023₱49.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - ALAMINOS - BOLINAO RD - K0322 + 328 - K0323 + 793 AT BARANGAY POGO, ALAMINOS CITY, PANGASINAN

Pangasinan 1st DEO, Region I

2024₱42.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - ALAMINOS - BOLINAO RD - K0337 + 000 - K0339 + 632, K0340 + 530 - K0341 + 822 AT BANI, PANGASINAN

Pangasinan 1st DEO, Region I

2023₱40.2M
Reported complete (DPWH)
View all 415 projects →

4. Implementation

Contract Amount

₱9,870,007.80

Progress

Reported complete (DPWH)

Start Date

August 23, 2019

Target End

December 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.