Roads23BH0014

001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0312 + 000 - K0313 + 000

001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0312 + 000 - K0313 + 000 is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱16,106,532.09. Status: Reported complete (DPWH). Contractor on record: MAR-DEB CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Santiago City, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

229 projects · ₱6.7B total · 0 flags

4. Implementation

Contract Amount

₱16,106,532.09

Progress

Reported complete (DPWH)

Start Date

March 2, 2023

Target End

May 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.