Buildings and Facilities22FB0164

LOCAL PROGRAM: CONSTRUCTION OF EVACUATION CENTER, BRGY. POBLACION, RAPU-RAPU, ALBAY

LOCAL PROGRAM: CONSTRUCTION OF EVACUATION CENTER, BRGY. POBLACION, RAPU-RAPU, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱6,784,508.42. Status: Reported complete (DPWH). Contractor on record: 3DIAMONDS CONST CORP 35457. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Suha Flood Control Dike, Camalig, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35457

55 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0505+419-K0505+600, K0509+704-K0510+912, GUINOBATAN, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱100.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM(BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SAN FRANCISCO RIVER FLOOD MITIGATION STRUCTURES, BRGY. MAGUIRON AND BRGY. M

Albay 3rd DEO, Region V

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER V-2022: 1.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (LEFT SIDE) GUINOBATAN, ALBAY; AND 2.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (RIGHT SIDE) GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2022₱98.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF NASISI RIVER FLOOD MITIGATION STRUCTURE, BARANGAY NABONTON, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2024₱96.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALON

Albay 3rd DEO, Region V

2025₱94.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALONG QU

Albay 3rd DEO, Region V

2025₱89.3M
Past target date (DPWH On-Going)
View all 55 projects →

4. Implementation

Contract Amount

₱6,784,508.42

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

August 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.