ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALONG QU
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALONG QU is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱89,348,790.16. Status: Past target date (DPWH On-Going). Contractor on record: 3DIAMONDS CONST CORP. Figures trace to dpwh.