Construction of Drainage Structure22DD0258

Construction of Drainage System, Barangay Tipacan, Lipa City, Batangas

Construction of Drainage System, Barangay Tipacan, Lipa City, Batangas is a DPWH-tracked public work in LIPA CITY (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱6,722,480.66. Status: Reported complete (DPWH). Contractor on record: KEASCIA CONST & SUPPLY. Figures trace to sumbong.

LIPA CITY (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Structures protecting Public Infrastructures/ Facilities at Barangay Quezon, Lipa City, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002896

₱3,239,614,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002775

₱103,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002639

₱70,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003167

₱40,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002797

₱32,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱6,722,480.66

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

July 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.