Construction of Flood Mitigation Structure24BD0100

Pinacanauan River Flood Management Projects, Caggay, Tuguegarao City, Cagayan

Pinacanauan River Flood Management Projects, Caggay, Tuguegarao City, Cagayan is a DPWH-tracked public work in TUGUEGARAO CITY (CAPITAL) (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱34,300,000.00. Status: Reported complete (DPWH). Contractor on record: D J D CONST INC FORMERLY: D J D CONST. Figures trace to sumbong.

TUGUEGARAO CITY (CAPITAL) (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Pinacanauan River Flood Management Projects, Caggay, Tuguegarao City, Cagayan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010609

₱1,460,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000958

₱1,032,937.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0006668

₱314,296.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0006667

₱3,282,020.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0006165

₱233,618.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010620

₱135,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000959

₱95,023.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000069

₱264,367.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

43 projects · ₱510.8M total · 0 flags

4. Implementation

Contract Amount

₱34,300,000.00

Progress

Reported complete (DPWH)

Start Date

May 24, 2024

Target End

October 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.