Buildings and Facilities24O00046

REHABILITATION/RETROFITTING OF SCHOOL OF URBAN AND REGIONAL PLANNING (SURP), UNIVERSITY OF THE PHILIPPINES, DILIMAN, QUEZON CITY, PHASE II

REHABILITATION/RETROFITTING OF SCHOOL OF URBAN AND REGIONAL PLANNING (SURP), UNIVERSITY OF THE PHILIPPINES, DILIMAN, QUEZON CITY, PHASE II is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱23,518,557.56. Status: Past target date (DPWH On-Going). Contractor on record: FERDSTAR BUILDERS INC. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

139 projects · ₱8.9B total · 1 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS-CONSTRUCTION OF RING DIKE WITH PUMPING STATION (PHASE 2 & 4), MACABEBE-MASANTOL, PROVINCE OF PAMPANGA

Region III, Region III

2024₱354.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 3, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ABACAN RIVER, DIKING AND SLOPE PROTECTION WORKS-PHASE 2, MEXICO, PAMPANGA

Region III, Region III

2025₱170.1M
Past target date (DPWH On-Going)
No sat.

PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, CONTRACT PACKAGE NO. 4-B, RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 15+700 TO STA. 15+957 (PHASE 2), RIGHT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2022₱148.4M
Reported complete (100% progress, DPWH status On-Going)

Flood Control Works - Diking/Slope Protection of Pasig-Potrero River, Bacolor and Porac, Pampanga

PORAC (PAMPANGA), PAMPANGA, Region III

2023₱144.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2020₱144.7M
Reported complete (DPWH)
View all 139 projects →

4. Implementation

Contract Amount

₱23,518,557.56

Progress

Past target date (DPWH On-Going)

Start Date

November 26, 2024

Target End

August 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.