Roads23PA0036

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0475+200-K0475+700

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0475+200-K0475+700 is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱77,197,149.41. Status: Reported complete (DPWH). Contractor on record: SILVERWOLVES CONST CORP. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

179 projects · ₱19.9B total · 9 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. SALAWAG, DASMARIÑAS, CAVITE

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. PALIPARAN III, DASMARIÑAS, CAVITE (PHASE I)

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+368 - K0283+475

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+475 - K0283+575

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG BAUANG-BAGUIO CITY ROAD, K0261+100 - K0261+300, K0262+300 - K0262+400, K0262+900 - K0263+100, K0263+500 - K0263+900, K0269+600 - K0269+750,

Region I, Region I

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OC

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 179 projects →

4. Implementation

Contract Amount

₱77,197,149.41

Progress

Reported complete (DPWH)

Start Date

June 27, 2023

Target End

February 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.