Bridges20FK0017

NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CASTILLA BYPASS ROAD, PACKAGE 2 CASTILLA, SORSOGON

NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CASTILLA BYPASS ROAD, PACKAGE 2 CASTILLA, SORSOGON is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱79,600,752.61. Status: Reported complete (DPWH). Contractor on record: MGT BUILDER'S & SUPPLY. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Salvador H. Escudero III Diversion Road, Sorsogon River, Downstream, Sorsogon City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Sorsogon DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

7 projects · ₱588.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY CANJELA TO B

Sorsogon DEO, Region V

2025₱141.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF BRGY. PINEDA-BRGY. SAN RAFAEL ROAD, PILAR

Sorsogon DEO, Region V

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-CUMADCAD-MACALAYA PORT ROAD, CASTILLA, SORSOGON

Sorsogon DEO, Region V

2022₱95.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONST. OF 2-STOREY SCHOOL BUILDING, 12 CLASSROOM (PILAR I CENTRAL SCHOOL), PILAR, SORSOGON

Sorsogon DEO, Region V

2024₱62.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CLUSTER XII-CONST./REPAIR/REHAB./IMPV'T. OF VARIOUS INFRASTRUCTURE INLCUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONSTRUCTION OF BANTAYAN-PANGPANG ROAD INCLUDING DRAINAGE, CONST. OF PALANAS-MALBOG ROAD INCLUDING DRAINAGE, CONST. OF PANGPANG

Sorsogon DEO, Region V

2018₱57.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CASTILLA BY-PASS ROAD PACKAGE I CASTILLA, SORSOGON

Sorsogon DEO, Region V

2020₱55.8M
Reported complete (DPWH)
View all 7 projects →

4. Implementation

Contract Amount

₱79,600,752.61

Progress

Reported complete (DPWH)

Start Date

March 11, 2020

Target End

November 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.