Buildings and Facilities20FO0022

CONSTRUCTION OF MULTI-PURPOSE BUILDING, GABON, POLANGUI, ALBAY

CONSTRUCTION OF MULTI-PURPOSE BUILDING, GABON, POLANGUI, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱2,924,882.73. Status: Reported complete (DPWH). Contractor on record: MIRCONS CONST AND SUPPLIES 38321. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,924,882.73

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

August 14, 2020

5. Audit