Buildings and Facilities19HJ0063

CONSTRUCTION OF 3 UNITS ONE STOREY THREE CLASSROOM SCHOOL BUILDING W/ TOILET ATTACHED AT EACH CLASSROOM (9.5MX27.0M) AT NABILOG ES, NABILOG, TAYASAN, NEGROS ORIENTAL

CONSTRUCTION OF 3 UNITS ONE STOREY THREE CLASSROOM SCHOOL BUILDING W/ TOILET ATTACHED AT EACH CLASSROOM (9.5MX27.0M) AT NABILOG ES, NABILOG, TAYASAN, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱14,924,537.03. Status: Reported complete (DPWH). Contractor on record: VVER CONST DEVELOPMENT CORP. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱175.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF ONE(1) UNIT FOUR (4) STOREY WORKSHOP BUILDING AT MASULOG HS (7.0MX 23.0M PLUS CORRIDOR 2.50M), CANLAON CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱21.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ONE UNIT FOUR STOREY WORKSHOP BUILDING AT MALAIBA HIGH SCHOOL (7.0M X 23M PLUS CORRIDOR 2.50M) CANLAON CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱21.6M
Reported complete (DPWH)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING (GYM), BARANGAY POBLACION, STA. CATALINA, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2021₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- BRGY. IMELDA TO BRGY. HINAKPAN ROAD CONNECTING GUIHULNGAN TO BALOC ISABELA ROAD IN SUPPORT OF THE COFFEE AND BANANA PROCES

Negros Oriental 1st DEO, Negros Island Region

2019₱11.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES BRGY. IMELDA TO BRGY. HINAKPAN ROAD CONNECTING GUIHULNGAN TO BALOC ISABELA ROAD IN SUPPORT OF THE COFFEE AND BANANA PROCESSOR

Negros Oriental 1st DEO, Negros Island Region

2020₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BAYAWAN COASTAL ROAD (VILLAREAL-CARANOCHE SECTION) LEADING TO BAYAWAN BEACH AND COA

Negros Oriental 3rd DEO, Negros Island Region

2022₱9.8M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱14,924,537.03

Progress

Reported complete (DPWH)

Start Date

August 28, 2019

Target End

November 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.