Buildings and Facilities16EG0064

CONSTRUCTION OF CLASSROOMS, (2STY12CL) SCHOOL BUILDING, MANGINGISDA NHS, PUERTO PRINCESA CITY

CONSTRUCTION OF CLASSROOMS, (2STY12CL) SCHOOL BUILDING, MANGINGISDA NHS, PUERTO PRINCESA CITY is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱15,720,607.08. Status: Reported complete (DPWH). Contractor on record: PTK GROUP INC. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱15,720,607.08

Progress

Reported complete (DPWH)

Start Date

September 15, 2016

Target End

March 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.