Flood Control and Drainage25EG0041

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IRAAN RIVER DOWNSTREAM, BRGY. POBLACION, ABORLAN, PALAWAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IRAAN RIVER DOWNSTREAM, BRGY. POBLACION, ABORLAN, PALAWAN is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱47,026,322.43. Status: Reported complete (DPWH). Contractor on record: PTK GROUP INC. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Iraan River Downstream, Brgy. Poblacion, Aborlan, Palawan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Palawan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,026,322.43

Progress

Reported complete (DPWH)

Start Date

April 7, 2025

Target End

October 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.