Buildings and Facilities19JF0053

CONSTRUCTION OF COVERED COURT, BRGY. MAGSAYSAY, MUNICIPALITY OF R.T. LIM, ZAMBOANGA SIBUGAY

CONSTRUCTION OF COVERED COURT, BRGY. MAGSAYSAY, MUNICIPALITY OF R.T. LIM, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱1,971,316.01. Status: Reported complete (DPWH). Contractor on record: GJD CONST. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,971,316.01

Progress

Reported complete (DPWH)

Start Date

July 19, 2019

Target End

September 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.