CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD OF BARANGAY II-A, BARANGAY UPA AND BARANGAY BABU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD OF BARANGAY II-A, BARANGAY UPA AND BARANGAY BABU is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: PRIME MOVER'S PHILS CONST AND SUPPLIES INC. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures Along San Juan River - Phase 5, Tanauan - Sto. Tomas, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

57 projects · ₱338.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY LOOB PROVINCIAL/NATIONAL ROAD, BARANG

Batangas 3rd DEO, Region IV-A

2023₱14.8M
Reported complete (DPWH)
No sat.

OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, PUROK 5, BARANGAY UPA, MATAAS NA KAHOY, BAT

Batangas 3rd DEO, Region IV-A

2025₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY 3, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY 1, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LOOB, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
View all 57 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

March 23, 2023

Target End

September 18, 2023

5. Audit