Roads19PC0049

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, SAN CARLOS PALALI-MALEKKEG ROAD IN SUPPORT OF CASSAVA, CORN, RICE, MANDARIN, TOURISM, HANDICRAFT, FURNITURE AND COCONUT, SANTA MARCELA, APAYAO

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, SAN CARLOS PALALI-MALEKKEG ROAD IN SUPPORT OF CASSAVA, CORN, RICE, MANDARIN, TOURISM, HANDICRAFT, FURNITURE AND COCONUT, SANTA MARCELA, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,497,311.28. Status: Reported complete (DPWH). Contractor on record: ISNAG BUILDERS. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-19-0006576

₱44,912,000.00 · FY2019

Released to Apayao 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

88 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS - APAYAO (CALANASAN) - ILOCOS NORTE RD - (S00644LZ) CHAINAGE 6571 - CHAINAGE 8322

Apayao 2nd DEO, Cordillera Administrative Region

2023₱84.5M
Reported complete (DPWH)
No sat.

CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-SAN ISIDRO SUR-POBLACION-LAPPA-MARAG-CADACLAN-SALAGUNTING TOURISM ROAD LEADING TO MANACOTA UNDERGROUND RIVER & OTHER TOURISM

Apayao 2nd DEO, Cordillera Administrative Region

2023₱82.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF KARAGAWAN RIVER FLOOD CONTROL, STA. 80+321 - STA. 81+162 (R/S), KARAGAWAN,

Apayao 1st DEO, Cordillera Administrative Region

2024₱74.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO RD-K0712+000-K0712+144, K0712+228-713+383 - AT SPECIFIC LOCATIONS ALONG CLAVERIA-CALANASAN-KABUGAO RD (S00631LZ)

Apayao 2nd DEO, Cordillera Administrative Region

2022₱67.6M
Reported complete (DPWH)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION/IMPROVEMENT OF CALABIGAN-CAGANDUNGAN ROAD, BRGY CAGANDUNGAN & BRGY CALABIGAN, LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱66.1M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS - TERTIARY ROADS CLAVERIA-CALANASAN-KABUGAO ROAD K0710+539 - K0711+061, K0711+126 - K0711+868

Apayao 2nd DEO, Cordillera Administrative Region

2022₱62.0M
Reported complete (DPWH)
View all 88 projects →

4. Implementation

Contract Amount

₱9,497,311.28

Progress

Reported complete (DPWH)

Start Date

June 10, 2019

Target End

December 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.