Construction of Flood Mitigation Structure24CI0053

Construction of Retaining Wall along Abacan Road Dike, Angeles City, Pampanga

Construction of Retaining Wall along Abacan Road Dike, Angeles City, Pampanga is a DPWH-tracked public work in ANGELES CITY (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱77,193,423.34. Status: Reported complete (DPWH). Contractor on record: THREE-IN-ONE CONST & TRADING. Figures trace to sumbong.

ANGELES CITY (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure with Road Dike along Sabangbalen River Phase 1, Mabalacat City, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008254

₱1,156,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017639

₱458,088.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018104

₱90,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0018317

₱121,051.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008256

₱107,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008158

₱156,487.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱77,193,423.34

Progress

Reported complete (DPWH)

Start Date

March 14, 2024

Target End

October 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.