Flood Control and Drainage20OG0001

REHABILITATION OF BUAYA TO EVANGELISTA CREEK, QUEZON CITY

REHABILITATION OF BUAYA TO EVANGELISTA CREEK, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱2,846,492.27. Status: Reported complete (DPWH). Contractor on record: V S CERDON IRON WORKS. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱31,800,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Flood Control Structure at Matalahib Creek, Quezon City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon City 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

10 projects · ₱39.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING IN ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱8.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CLASSROOMS (BATCH 13) MINALABAC NHS, MINALABAC, CAM. SUR

Camarines Sur 2nd DEO, Region V

2016₱8.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN IGNACIO, ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱5.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN ROQUE, ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱4.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION, IMPROVEMENT AND REHABILITATION OF MULTI-PURPOSE BUILDINGS WITH SITE DEVELOPMENT, BARANGAY BLUE RIDGE B, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2021₱4.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 2 STOREY BARANGAY MULTI-PURPOSE BUILDING, BARANGAY BLUE RIDGE B, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2020₱3.5M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱2,846,492.27

Progress

Reported complete (DPWH)

Start Date

February 7, 2020

Target End

May 6, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.