Flood Control and Drainage17G00094

CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITHIN BAGO RIVER BASIN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITHIN BAGO RIVER BASIN is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱1,234,753.08. Status: Reported complete (DPWH). Contractor on record: SILVERROCK CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

98 projects · ₱377.5M total · 0 flags

4. Implementation

Contract Amount

₱1,234,753.08

Progress

Reported complete (DPWH)

Start Date

November 20, 2017

Target End

December 26, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.