Roads23DJ0064

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BRGY. MAMALA 1, SARIAYA, QUEZON

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BRGY. MAMALA 1, SARIAYA, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Past target date (DPWH On-Going). Contractor on record: ROMHEAD S J BUILDERS AND DEVELOPMENT INC. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure, Villa Altamira, Brgy. 11, Lucena City, Quezon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Quezon 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

181 projects · ₱3.1B total · 0 flags

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Past target date (DPWH On-Going)

Start Date

May 9, 2023

Target End

February 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.