Bridges22N00025

TAGO - LA PAZ BYPASS ROAD, SURIGAO DEL SUR

TAGO - LA PAZ BYPASS ROAD, SURIGAO DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱101,269,833.83. Status: Reported complete (DPWH). Contractor on record: ADFIL CORP. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

215 projects · ₱22.1B total · 2 flags

4. Implementation

Contract Amount

₱101,269,833.83

Progress

Reported complete (DPWH)

Start Date

September 28, 2022

Target End

October 31, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.