Construction of Flood Mitigation Structure22NG0023

Construction of Magtiaco River Flood Control Structure along Magtiaco Bridge (Phase 2), Barangay San Pedro, Alegria, Surigao del Norte

Construction of Magtiaco River Flood Control Structure along Magtiaco Bridge (Phase 2), Barangay San Pedro, Alegria, Surigao del Norte is a DPWH-tracked public work in ALEGRIA (SURIGAO DEL NORTE), SURIGAO DEL NORTE, Region XIII. Reported contract value: ₱39,180,150.39. Status: Reported complete (DPWH). Contractor on record: JMT CONST. Figures trace to sumbong.

ALEGRIA (SURIGAO DEL NORTE), SURIGAO DEL NORTE, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Magtiaco River Flood Control Structure along Magtiaco Bridge (Phase 2), Barangay San Pedro, Alegria, Surigao del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003131

₱66,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱39,180,150.39

Progress

Reported complete (DPWH)

Start Date

February 11, 2022

Target End

September 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.