Roads24BK0047

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTRE PROGRAM - ROLL-IT) MALDANUM - SAN BERNABE ROAD CONNECTING

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTRE PROGRAM - ROLL-IT) MALDANUM - SAN BERNABE ROAD CONNECTING is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱9,501,875.85. Status: Reported complete (DPWH). Contractor on record: JHUERS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Addalam River Flood Control, Downstream ( Disiluad Section ) , Aglipay, Quirino
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quirino DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

32 projects · ₱266.9M total · 0 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CORDON - AURORA BDRY RD (ISABELA BDRY - JCT DUMABATO) - KO339+000 - K0345+338, CABARROGUIS AND AGLIPAY,

Quirino DEO, Region II

2025₱29.3M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF RIVER FLOOD CONTROL AT NALUNGTUTAN BRIDGE (SAN DIONISIO II SECTION), NAGTIPUNAN, QUIRINO

Quirino DEO, Region II

2025₱28.1M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MADDELA DISTRICT HOSPITAL, MADDELA, QUIRINO

Quirino DEO, Region II

2024₱19.8M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ECHAGUE - JONES - MADDELA RD (VILLA NORTE - PANANG SECT) - K0377+(-859) - K0380+298, MADDELA, QUIRINO

Quirino DEO, Region II

2025₱19.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG MANGANDINGAY - SAGUDAY ISABELA BDRY RD - K0336+(-310) - K0340+334, DIFFUN AND SAGUDAY, QUIRINO

Quirino DEO, Region II

2025₱19.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF THE LEGISLATIVE BUILDING IN THE MUNICIPALITY OF DIADI, PROVINCE OF NUEVA VIZCAYA

Nueva Vizcaya DEO, Region II

2025₱19.2M
Past target date (DPWH On-Going)
View all 32 projects →

4. Implementation

Contract Amount

₱9,501,875.85

Progress

Reported complete (DPWH)

Start Date

March 11, 2024

Target End

June 24, 2024