Water Provision and Storage24J00280

IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II, SITIO TEGGEP, BARANGAY MASOLA, SAMPINIT COMPLEX, ISABELA CITY, BASILAN

IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II, SITIO TEGGEP, BARANGAY MASOLA, SAMPINIT COMPLEX, ISABELA CITY, BASILAN is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱9,944,613.10. Status: Past target date (DPWH On-Going). Contractor on record: HHH DEVELOPER AND CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,944,613.10

Progress

Past target date (DPWH On-Going)

Start Date

December 11, 2024

Target End

March 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.