Roads23LD0060

CONSTRUCTION OF PEDESTRIAN OVERPASS ALONG DAVAO-COTABATO ROAD (JCT. DIGOS-COTABATO SECTION), SPAC SECTION, MATANAO, DAVAO DEL SUR

CONSTRUCTION OF PEDESTRIAN OVERPASS ALONG DAVAO-COTABATO ROAD (JCT. DIGOS-COTABATO SECTION), SPAC SECTION, MATANAO, DAVAO DEL SUR is a DPWH-tracked public work in Davao del Sur DEO, Region XI. Reported contract value: ₱29,400,000.00. Status: Past target date (DPWH On-Going). Contractor on record: HYDROPURE TECH PHILIPPINES CORP. Figures trace to dpwh.

Davao del Sur DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagum - Libuganon River, Talomo, Sto. Tomas, Davao del Norte (Phase 1)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Davao del Sur DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

11 projects · ₱231.0M total · 0 flags

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2023

Target End

March 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.