Roads25IJ0012

OO1: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, SECONDARY ROADS - CALBAYOG - CATARMAN RD. - K0785+(-261) - K0785+(-199), K0788+311 - K0788+368, SAMAR

OO1: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, SECONDARY ROADS - CALBAYOG - CATARMAN RD. - K0785+(-261) - K0785+(-199), K0788+311 - K0788+368, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱2,650,580.50. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RAS EASTERN BUILDERS DEVELOPMENT CORP. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Gandara River, Phase II, Barangay Tawiran, Gandara, Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Samar 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,650,580.50

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 6, 2025

Target End

July 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.