Buildings and Facilities21GN0018

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ABUANAN, BAGO CITY, NEGROS OCCIDENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ABUANAN, BAGO CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱3,840,794.76. Status: Reported complete (DPWH). Contractor on record: JAIME B CHING ENT. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Bago River, Negros Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Occidental 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

400 projects · ₱12.8B total · 44 flags

4. Implementation

Contract Amount

₱3,840,794.76

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

June 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.