Roads24A00034

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG - SAN FERNANDO - SAN JUAN BYPASS ROAD, (BAUANG SECTION), PACKAGE 1, LA UNION

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG - SAN FERNANDO - SAN JUAN BYPASS ROAD, (BAUANG SECTION), PACKAGE 1, LA UNION is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱178,349,997.76. Status: Reported complete (DPWH). Contractor on record: BONIMAR CONST ENT. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱178,349,997.76

Progress

Reported complete (DPWH)

Start Date

February 26, 2024

Target End

March 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.