Flood Control and Drainage24CC0341

CONSTRUCTION OF DRAINAGE SYSTEM, VIOLETA AVENUE AND SAMPAGUITA STREET, BARANGAY STA. CRUZ, GUIGUINTO, BULACAN

CONSTRUCTION OF DRAINAGE SYSTEM, VIOLETA AVENUE AND SAMPAGUITA STREET, BARANGAY STA. CRUZ, GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱23,999,725.07. Status: Past target date (DPWH On-Going). Contractor on record: SAMJS CONST SERVICES. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,999,725.07

Progress

Past target date (DPWH On-Going)

Start Date

June 25, 2024

Target End

November 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.