GAA 2023 OO-223J00140

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TUMAGA RIVER FLOOD CONTROL (GUIWAN-TUGBUNGAN SECTION) WITH ESPLANADE, PACKAGE 2, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱143,231,584.11. Status: Past target date (DPWH On-Going). Contractor on record: PYRAMID CONSOLIDATED BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

131 projects · ₱5.8B total · 0 flags

4. Implementation

Contract Amount

₱143,231,584.11

Progress

Past target date (DPWH On-Going)

Start Date

August 31, 2023

Target End

April 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.