Flood Control and Drainage20ED0080

CONSTRUCTION OF MAIDLANG SEAWALL, BRGY. MAIDLANG, CALAPAN CITY, ORIENTAL MINDORO

CONSTRUCTION OF MAIDLANG SEAWALL, BRGY. MAIDLANG, CALAPAN CITY, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱14,579,997.66. Status: Reported complete (DPWH). Contractor on record: AB1 MEGA BUILDERS INC. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱31,671,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Drainage System, Mulawin-Arangin Armouring, Naujan, Oriental Mindoro
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Mindoro Oriental DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,579,997.66

Progress

Reported complete (DPWH)

Start Date

November 30, 2020

Target End

May 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.