Buildings and Facilities19HI0083

CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY POBLACION, SOGOD, CEBU

CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY POBLACION, SOGOD, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱2,400,750.00. Status: Reported complete (DPWH). Contractor on record: SAN NARCISO BUILDERS CORP FOR SAN NARCISO 24527. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,400,750.00

Progress

Reported complete (DPWH)

Start Date

January 9, 2020

Target End

April 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.