CONSTRUCTION OF BATANGAS ACCESS ZONE - WEST SIDE (PHASE 1), BATANGAS CITY, SAN PASCUAL AND BAUAN BATANGAS is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱74,304,987.50. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TCSC CORP 15453. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 15453

214 projects · ₱15.5B total · 0 flags

Other projects by this contractor

View all 214 projects →

4. Implementation

Contract Amount

₱74,304,987.50

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 24, 2023

Target End

June 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.